WBM is part of the crust whereas GSB is considered as Sub base. GSB is laid in a layer and compacted duly controlling moisture. For WBM coarse aggregates are spread initially and compacted. Fines are spread later and watered down in to the compacted aggregate.

What is the first step in road construction?

Steps in Bituminous Road Construction

  1. Preparation of the existing base course layer.
  2. Application of Tuck Coat.
  3. Preparation and placing of Premix.
  4. Rolling.
  5. Quality control of bituminous concrete construction.
  6. Finished surface.

What is the first stage in route selection?

First, the highway designer reviews topographic, geologic and soil maps as well as available aerial photographs of the area. The designer looks for conditions that will require sudden changes in alignment.

READ ALSO:   Do cars go faster with big or small wheels?

What is WMM in civil engineering?

WBM(Water Bound Macadam) conventional method and WMM(Wet Mix Macadam) modern technology- are base course layers for Pavement/Road design. In case of WBM stone aggregates and binders are overlaid on one another at the time of construction.

Which layer is constructed above embankment is called?

Civil Engineering (CE) Question The embankment is the lowest layer and it is below the sub grade, base is above sub base, sub base is above the sub grade.

What is the first step in a preliminary survey?

Explanation: The first step in preliminary survey is to establish primary traverse followed by a survey and detailed project report.

What is difference between GSB and WBM in road construction?

GSB or Granular Sub Base is sub base course of road layer whic acts as a filter media for water runoff and WBM or Water Bound Maccadam is layer which is laid above GSB and Below Bituminous Layer on roads with low traffic Denaity and acts as interlocking Layer Originally Answered: What is the difference between GSB and WBM in road construction?

READ ALSO:   Can you take mental health medication while pregnant?

Which one is laid first GSB or GSB?

GSB is laid first. GSB is the drainage layer which shoild be laid just over subgrade to cut off capillary water risig from the soil beneath. It also discharges water that has percolated from the surface to the adjacent drains which would otherwise get into subgrade and weaken it.

What is the function of GSB layer in road?

It is the part of foundation layer of the road pavement. Major purpose for GSB layer is filter layer and drainage layer. Also it serves purpose of load distribution to subgrade.

What is GSB in drainage system?

GSB is the drainage layer which shoild be laid just over subgrade to cut off capillary water risig from the soil beneath. It also discharges water that has percolated from the surface to the adjacent drains which would otherwise get into subgrade and weaken it.